Your Councillors are pleased to report that Thames Water are making good progress with the first phase of their water main replacement project at Leaves Green Road and is looking to move into their second phase by the end of this week.
The first phase has finished nine days earlier than expected, so it is a positive start to the works.
The multi-phased signals on the Downe Road / Westerham Road roundabout will be reduced to two-way phased signals as the works move further along Leaves Green Road towards Biggin Hill.
Thames Water will continue to operate the signals manually at peak times during all phases of their works.
Cllr Alexa Michael said: “We are expecting the next phase of works to be in place for up to five or six weeks and will share more information from Thames Water when we have further updates to share.”
If residents wish to contact Thames Water to enquire/complain/compliment them on their works at Leaves Green Road, Keston, they can contact customer.feedback@thameswater.co.uk – quoting BB00993673 or their permit reference number – MU034 BIGGINHILL-LGR.